SEOUL, Jan 23 (Reuters) - Samsung Engineering Co Ltd

028050.KS said on Thursday it won a $441 million order to build a power plant in Chile from a consortium of Korea Southern Power Co Ltd (KOSPO) Href="NewsSearch">KEPCOS.UL and Samsung C&T Corp

000830.KS .

The KOSPO-Samsung C&T consortium won the original order for the power plant from BHP Billiton's BHP.AX Chile unit in November 2013, the engineering firm said in a statement.

The power plant, with a production capacity of 517 megawatts, is expected to be completed in 2016 to provide electricity for a BHP Billiton copper mine.

Samsung C&T and Samsung Engineering are affiliates that are both part of Samsung Group SAGR.UL .

(Reporting by Joyce Lee; Editing by Miral Fahmy)

((jungyoon.lee@thomsonreuters.com)(+82 2 3704 5609)(Reuters Messaging: jungyoon.lee.thomsonreuters.com@reuters.net))

Keywords: SAMSUNGENGINEERING ORDER/CHILE

URN: 
urn:newsml:reuters.com:20140123:nL3N0KX1M1:3
Topics: 
ELEU GB CMPNY INDS MINE UTIL ENR TRAD RTRS MIS MIN COMA BMAT MUL EUROPE ENER COEN MEMI KR MET AU EUROP WHO EMRG CON ASIA LEN WEU MTAL ISER LATAM AMERS CL

Contact Us

Due to the security nature of our business, personal meetings are only by pre-arranged appointment.
Phone at any time on

1300 987 995

info@ausmint.com